                                                                  Site Daily Report
Project: LYP’s Residence  
Contractor: PISNOKA International Corporation 
Date:  23-July-2019
 
No: LYP-280
Average number of workers 

            Management                :   1
            Supervisor/ Engineers   :   3
            HSE                               :   2
            MEP Staff                      :   2
            Archicture                      :  1
            Office Staff                    :   2
            Un-skilled                      :   150
            Sub Contractor              :   30
                                                                       Equipment                                                                      

- Wheel Loader (1)                                                

- 25 Ton Crane (1)

- 55 Ton Crane (1)

- Roller (1)

- Bulldozer (1)

- Dumping truck (1)

- Excavator

- Tower Crane 
                                                                 Machinery on site:

-Cutting machine gas (2)

-Grinding machine (3)

-Cutting motor (9)

-Generator GT 60 kva (1)

-Generator GT 30 kva (2)

-Generator GT 150 kva (1)

-Generator GT 250 kva (1)
-Flat compactor (4)
                                                                 Works Carried Out:

1)    Temporary site facility

  • Temporary Work Camp                                           
  • Temporary House keeping

2)    Security House I&II

·         Bricklaying for Molding

·         Plastering for Molding

·         Steel Structure Work

3)    Car Parking, I&II

·         Brick Laying

·         Plastering Work

·         Apply Waterproofing of Gutter

·         Steel Structure Work

4)    Dinning Pool
Steel Structure Work for roof tile
5)    Grand House

·         Bricklaying

·         Remove Formwork of Second Floor Beam

·         Install Rebar and Formwork of Lintel

·         Installation Scaffolding for Supporting First Floor Beam

·         Cleaning Surface Concrete gutter

·         Apply Waterproofing (Brush Bound)

·         Mortar Topping with Slope of Roof Gutter

·         Casting Concrete of First Floor Beam

6)    Fitness