SOIL EXCAVATION CALCULATION SCHEDULE FOR GENERATOR ROOM
No Item Item Number DIMENSION  VOLUME REMARK
pcs W(m) L(m) H (m) (m3)
(a) (b) ( c )  ( d )  ( e) (f) ( g= c x d x e x f ) ( h)
Soil Excavation of Generator Room
I. Foundation
1 F1 (A-1) 1 1.60 1.60 2.40 6.144 Offset 0.5m around working area
2 F1 (A-2) 1 1.60 1.60 1.50 3.840
3 F1 (A-3) 1 1.60 1.60 1.50 3.840
4 F1 (A-4) 1 1.60 1.60 1.50 3.840
5 F1 (B-1) 1 1.60 1.60 1.50 3.840
6 F1 (B-2) 1 1.60 1.60 1.50 3.840
7 F1 (B-3) 1 1.60 1.60 1.50 3.840
8 F1 (B-4) 1 1.60 1.60 1.50 3.840
9 F1 (C-1) 1 1.60 1.60 1.50 3.840
10 F1 (C-2) 1 1.60 1.60 1.50 3.840
11 F1 (C-3) 1 1.60 1.60 1.50 3.840
12 F1 (C-4) 1 1.60 1.60 1.50 3.840
Total 48.384
II. Ground Slab
1 Pit(0.6x2.5x1.2) 1 1.90 3.80 0.60 4.332 Level of Existing Soil=10.00m
2 Pit(0.4x1.2x1.2) 1 1.70 2.50 0.60 2.550
Total 6.882
Sub-Total 55.266

 
CRUSH STONE M30 CALCULATION SCHEDULE FOR GENERATOR ROOM
No Item Item
 Number
DIMENSION  VOLUME REMARK
pcs W(m) L(m) H(m) (m3)
(a) (b) ( c ) ( d )  ( e) (f) (g) =( c x d x e x f ) ( h )
Crushed Stone M30 at Generator Room
I. Foundation
1.80
1 F1 (A-1) 1 1 1 0.15 0.150 Offset 0.2m around working area
2 F1 (A-2) 1 1 1 0.15 0.150
3 F1 (A-3) 1 1 1 0.15 0.150
4 F1 (A-4) 1 1 1 0.15 0.150
5 F1 (B-1) 1 1 1 0.15 0.150
6 F1 (B-2) 1 1 1 0.15 0.150
7 F1 (B-3) 1 1 1 0.15 0.150
8 F1 (B-4) 1 1 1 0.15 0.150
9 F1 (C-1) 1 1 1 0.15 0.150
10 F1 (C-2) 1 1 1 0.15 0.150
11 F1 (C-3) 1 1 1 0.15 0.150
12 F1 (C-4) 1 1 1 0.15 0.150
II. Ground Slab and Beam 36.980
1 Slab Area 1 8.60 #### 0.25 36.980 Offset 0.2m around working area
Sub-Total 38.780